> > Apparently, they were reselling power back to ConEd during either the
> > blackout or 9/11, I can't remember which one. . .That how amazing their
> > generators are. . .and they're not sitting up on the roof either. . .a
> > well-thought out and comprehensive setup.
> I wouldn't trust their claim about reselling power but there's no doubt
> they were up. During big blackout, everyone who had gensets was up. During
> 9/11, only Telehouse went down (on 9/13) because their gensets overheated
> because debris were clogging the heat escape louvers.

This is true,  they were back feeding to coned.  They have enough power 
for their floor to power the entire building.  Inap @ 75broad was without 
any problems durring 9/11 and the blackout.  Contact me off list if anyone 
needs INAP contacts.

- Brandon

----------------------------------------------------------------------------